A solution that delivers
A total of 189 REHAU vertical sliding sash windows needed to be fitted by project installer Hadrian throughout the school. In addition to this, 40 replacement casement windows were required to the toilet blocks and external wellways, which the installer manufactured inhouse, with REHAU profiles.
As this project was to be carried out during term-time, ongoing works needed to cause minimal disruption for pupils, teachers and other on-site staff. Indeed, due to size of the windows – measuring 1200 x 3300mm and weighing in excess of 150kg – they had to be split into separate frames and coupled together on site. In order to ensure school activities during the day remained undisturbed, these product deliveries and joining activities occurred outside teaching hours.
Five Stars
The whole project was carried out over five phases, running from July 2020 to January 2021 in order to limit the impact on the school. Each phase was linked to the building elevations and was planned so that one classroom was released at a time, enabling the school to relocate pupils to different classrooms without impinging on teaching.
The five-phase approach was praised by Chris Martindale, Project Development Officer at Gateshead Council: “We were extremely impressed with how smoothly this project ran from the beginning to completion, especially given the complex circumstances involved.
He concludes: “As a client, I was able to leave everyone involved in this to carry out the works required – the fact I could do this, and still have the project delivered on time, was something I really appreciated. We would happily engage Hadrian again because their communication was excellent. Since the project was completed, everyone has been commenting on how good the windows look and the quality is top class, so we’re all really pleased.”